The Trench Keeps Coming Back to South Hilltop. Here's What Xcel Is Building Under Bayaud.

Thursday, October 29, is the last scheduled day of the closure on East Bayaud Avenue between South Clermont and South Bellaire. If you live on that stretch, this may sound familiar. The same blocks were fenced off in May, and so was South Birch Street between East Cedar and East Ellsworth. Both streets reopened over the summer. In mid-October the barricades went back up.

The cause is Xcel Energy's Leetsdale-Monroe-Elati project. Xcel is replacing a six-mile, 230-kilovolt underground transmission line across central and southeast Denver. Xcel describes a closure as lasting one to three weeks per block. In south Hilltop, the record shows a block can close more than once, and some closures run much longer than that average.

The Closure Record on Three Hilltop Streets

Street segment First scheduled window Status by mid-July Current scheduled window
E. Bayaud Ave., S. Clermont to S. Bellaire May 11 to June 17 Off the schedule Oct. 15 to Oct. 29
S. Birch St., E. Cedar to E. Ellsworth May 11 to June 1 Off the schedule Oct. 15 to Oct. 29
S. Birch St., E. Bayaud to E. Ellsworth June 17 to TBD Off the schedule Included in the segment above
E. Cedar Ave., S. Glencoe to S. Fairfax Not listed in June Not listed in July Aug. 19 to Oct. 16

The June dates come from Xcel's project schedule as archived on June 15, 2026. By the update dated July 15, neither Bayaud nor Birch appeared among the Phase 1 closures. The October windows come from the current project page, last updated October 13.

The Cedar Avenue closure is the clearest example of an average not matching a street. From August 19 to October 16 is about eight weeks, with the South Forest intersection closed too. That is well past the "one to three weeks" in Xcel's November 2025 public Q&A. The same document says some areas may take up to four weeks.

Why the Line Runs Under Residential Streets

Most of the old cable runs under Leetsdale Drive and Speer Boulevard. Xcel says it can't rebuild in that location for three reasons:

  • safety for drivers and crews in heavy traffic
  • the existing line has to stay energized during construction
  • there isn't enough room underground for a larger cable system

Xcel says the new route avoids "collector and aerial roadways" on purpose. The work therefore lands on smaller streets.

Phase 1 runs from the Leetsdale substation to the Monroe substation. Xcel's open-house map puts that stretch at 2.0 miles. Xcel's November 2025 Q&A lists these Phase 1 streets for temporary closures:

  • East Ellsworth Avenue
  • South Birch Street
  • East Cedar Avenue
  • South Glencoe Street
  • East Dakota Avenue
  • South Ivy Street
  • East Virginia Avenue
  • South Jersey Street

The plan is to start at the southeast end near Leetsdale and move northwest toward Monroe. That path cuts through the southern part of Hilltop. The Hilltop Neighborhood Association says the project "directly effects residents" of South Hilltop. It also told the rest of the neighborhood to expect intermittent street and sidewalk closures, detours, and excavation noise.

The Q&A also says Xcel works to avoid city-marked dedicated bike lanes. The neighborhood association's May update called the closed Bayaud segment "E Bayaud Ave aka the Bayaud Cycleway." If you ride that route, plan for the same closure dates drivers face.

A Block Gets Built in Stages

The repeat closures make more sense once you see the build order. Xcel's open-house display boards show these steps:

  1. Cut the pavement and dig the trench.
  2. Install the vaults and conduit.
  3. Backfill with concrete and slurry.
  4. Install the cable.
  5. Lay temporary pavement.
  6. Do the permanent restoration.

Xcel hasn't said which of these steps the October closures on Bayaud and Birch cover. The sequence does show why a reopened street isn't necessarily finished. Xcel's project page says work areas may stay temporarily restored after construction until final restoration can happen, as weather allows. A patched strip down the middle of your street is one of those in-between stages.

Even a single pass can stall. Xcel says shallow trenches go faster than deep ones. Finding undocumented utilities slows the work. Poor records of existing lines can stop work completely, sending crews to another location until engineers find a fix. The schedule says the same thing in a footnote. Dates can shift because of weather, materials, or "discovery of underground obstacles."

What a Closure Looks Like on Your Block

You get notice before a closure starts. Xcel says door hangers go up on homes next to the closure three to five business days ahead. Before work begins on a block, crews from BT Construction plan to knock on doors to ask about residents' needs.

Vault locations depend on the water, sewer, and gas lines already under the street. Because of that, Xcel plans to close each block in both directions for the length of the work. Here is what Xcel has committed to inside that closure:

  • Driveways and garages. Xcel plans to shrink the work area after business hours so you can reach your home and garage. You may be blocked while crews are working.
  • Midday trips. If you work from home and need to leave during work hours, tell the project team ahead of time and Xcel says it will work with you where it can.
  • Trash day. Xcel says it coordinates with Denver Waste Collection. Crews may move all the carts to one side of the street for pickup and will help return them if they were moved.
  • Sidewalks. Xcel plans to keep sidewalks open. If any part of a sidewalk is damaged or removed, Xcel says it will restore it to its previous condition, including ADA standards.
  • EV charging. If construction blocks access to your home EV charger, Xcel has a mobile charging pilot for eligible residents. It asks for seven days' notice when possible and requires a signed waiver.
  • Property damage. Xcel says its contractors will repair private property damaged by the work through a claims process. You can start a claim through the project email or phone line, or with the crew on site.

The current project page lists work hours as Monday through Friday, 7 a.m. to 7 p.m., and Saturday, 8 a.m. to 5 p.m. Evening, night, or Sunday work is possible in some cases. The Q&A adds that crews usually arrive around 7:30 a.m. and start machinery soon after.

After October 29

The Bayaud and Birch closures ending October 29 are the last ones on Xcel's current Phase 1 schedule. No next Hilltop street has been named yet. Ellsworth is the street to watch. It's on Xcel's Phase 1 list, and in June the District 5 newsletter listed several Ellsworth segments next to the Birch closure. Phase 1 is still scheduled to finish in spring 2027.

West of Hilltop, Phase 2 started in August and runs to spring 2028. It now has its own closures on East 4th Avenue between Fillmore and Clayton, on Circle Drive, and on Monroe Street between 2nd and 4th. If your daily drive heads toward Cherry Creek North, you'll hit both phases this fall. Xcel expects the full line to be in service in 2028.

Xcel's average closure time won't tell you when your block is done. Xcel updates its schedule weekly. For notices, join the project email list at [email protected] or call 303-716-8990, and add a week of slack to any listed end date.

This post is general information, not legal advice. If you're filing a damage claim, confirm the details with Xcel directly and talk to the right professional if you need to.

Planning to list a south Hilltop home while the trench is still moving through? Shelby Richardson can time your photos, showings, and listing date around the posted closure schedule. Schedule a market strategy call before your block shows up on the list.

Work With Shelby

Get assistance in determining current property value, crafting a competitive offer, writing and negotiating a contract, and much more. Contact me today.

Follow Me on Instagram